CivilJungle

  • Home
  • Civil
    • Detail A to C >>
      • Aggregate
      • Beam
      • Bitumen
      • Brick
      • Bridge
      • Cement
      • Civil
      • Column
      • Concrete
    • Detail D to I >>
      • Dampness
      • Design
      • Difference
      • Electrical
      • Excel Sheet
      • Flooring
      • Formwork
      • Foundation
      • Irrigation
    • Detail J to R >>
      • Mortar
      • Plaster
      • Pile
      • Plumbing
      • Quantity Survey
      • Reinforcement
    • Detail S to S >>
      • Sampling
      • Self Compact Concrete
      • Slab
      • Soil Mechanics
      • Staircase
      • Stone
      • Survey
    • Detail T to Z >>
      • Technology
      • Test
      • Transportation
      • Window
      • Wood
  • Difference
    • Difference Between A to C >>
      • Difference Between 33, 43 and 53 Grade Cement
      • Difference Between Asphalt and Bitumen
      • Difference Between Beam and Column
      • Difference Between Bitumen and Tar
      • Difference Between Bridge and Culvert
      • Difference Between Carpet Area and Built-up Area
      • Difference Between CPM and PERT/PERT Vs CPM
    • Difference Between F to L >>
      • Difference Between Fat Lime and Hydraulic Lime
      • Difference Between Flexible Pavement and Rigid Pavement
      • Difference Between Flyover and Bridge
      • Difference Between Footing and Foundation
    • Difference Between L to M >>
      • Difference Between Lap Length and Development Length
      • Difference Between Lime and Cement
      • Difference Between M Sand Vs River Sand
      • Difference Between M25 and M30 Concrete
      • Difference Between Mortar and Concrete
    • Difference Between N to P >>
      • Difference Between One Way Slab and Two Way Slab
      • Difference Between OPC Vs PPC
      • Difference Between Plasticizer And Superplasticizer in Civil
      • Difference Between Plinth Level, Sill Level, and Lintel Level.
    • Difference Between P to W >>
      • Difference Between Pre-Tensioning and Post-Tensioning
      • Difference Between Short Column and Long Column
      • Difference Between Timber And Wood
  • Excel Sheet
    • How to >>
      • How to Building Construction Process Step by Step
      • How to Calculate Slab Steel Quantity from Drawing | BBS of Slab
      • How to Calculate Staircas
      • How to Excavation Calculation in Excel Sheet
      • How to Find House Construction Cost
    • Building Estimation Step by Step In Excel Sheet
    • Estimation for Building Works
    • House Construction Cost Calculator Excel Sheet
    • House Construction Cost Calculator Excel Sheet For Ground Floor(G.F.), G.F.+1, G.F.+2, G.F.+3,
  • Tools
    • Rate Analysis >>
      • Rate Analysis of Aluminum Door
      • Rate Analysis of Wooden Door
      • Rate Analysis of Brick Work
      • Rate Analysis for Concrete
      • Rate Analysis for Dry Lean Concrete
      • Rate Analysis of Plastering
    • Brick Masonry Calculator
    • Calculator for Cutting Length of Stirrups
    • Concrete Material Calculator
    • House Construction Cost Calculator
    • Plaster Calculator
    • Steel Bar Calculation
    • Trapezoidal Footing Calculato
  • IS Code
    • Is 1200 Important Point Part-1
    • IS Code for Civil Engineer [Q&a]
    • IS 456 Most Important Point Part- 1
    • IS 516:1959 Most Important Point (Method of Tests For Strength of Concrete)
  • हिंदी

Rate Analysis of Plastering Calculator | What is Rate analysis of Plaster | How to Use Calculator

Rate Analysis of Plaster Work Calculator

Important Point

    • What is Rate Analysis?
    • How to Use Rate Analysis of Plaster Work Calculator?
      • Step – 1. Select Area 
      • Step – 2. Plaster Thickness
      • Step – 3. Plaster Ratio
      • Step – 4. Fill Labour Charges
      • Step – 5. Fill Material Rate as Per Actual
      • Step – 6. Additional Cost in Rate Analysis
      • Step – 7. Rate of Plaster as Per the Required Area
      • Step – 8. Print Button for Print Out
  • Rate Analysis of Plastering Calculator
    • Material Calcultion of Plaster Work
      • Material Calculation for Rate Analysis of Plaster
        • Cement calculation
        • Sand calculation
      • Labour for Rate Analysis of Plaster
      • Extra Work Calculation in Rate Analysis of plaster
    • Video tutorial for better understanding:

What is Rate Analysis?

The basis of arriving at a correct and reasonable rate per unit. Work or Supply for a particular item following its specification and detail survey of materials, labour, equipment, etc. as required for the unit work and their prevailing rates may be called as an analysis of rate.

How to Use Rate Analysis of Plaster Work Calculator?

This calculator is used for rate analysis of plaster work. Here we will see Step by step how this calculator works.

Step – 1. Select Area 

First Enter your Rate analysis area in Sq.m as per shown in the below picture.

Plaster Work Calculator s1

Step – 2. Plaster Thickness

Enter your Plaster Thickness in mm as per shown in the below picture.

Plaster thick

Step – 3. Plaster Ratio

Enter your Plaster work cement and sand ratio as per shown in the below picture.(cement and sand ratio in different cells)

Plaster ratio

 

Step – 4. Fill Labour Charges

Enter your Labour Charges Rate like Mason charges, Bhisti charges, and Coolie Charges as per shown in the below picture.( Mason, Bhisti, and Coolie Charges in different cells)

Labor Charges

 

Step – 5. Fill Material Rate as Per Actual

Enter your Material Rate like Cement and Sand as per shown in the below picture.( Enter Cement and Sand Both are in different cells)

Material rate

 

Step – 6. Additional Cost in Rate Analysis

Check your Further details like Wastage percentage, Scaffolding percentage, other extra charges, water charges and contractor profit percentage. if any are changed as per your requirement than change in cells that are shown in below cells.

Extra

 

Step – 7. Rate of Plaster as Per the Required Area

After Completing above 6 steps final answer given last two cells that’s are Cost of 100 Sq.m. that are shown in below picture. (round off figure also mention)

Wastge

Step – 8. Print Button for Print Out

if you required print your plastering work calculation you can use print button option.

Print Button

 

Rate Analysis of Plastering Calculator

Material Calcultion of Plaster Work

In this Rate Analysis of Plaster calculator calculates material, labor, wastage, and other charges in rate analysis.

Material Calculation for Rate Analysis of Plaster

Material calculation in Rate Analysis like Cement and sand

Cement calculation

Dry Cement mortar volume = 1.33 convert Wet cement. (The Plaster mortar dry volume of plaster decrease volume of dry cement mortar, so 1.33 time of dry mortar)

Wastage of cement mortar 33% (1.33) extra

So, Cement calculation requirement of cement = 1 * 1.33  = 1.33 cu.m,

Multiplay plaster thickmess  = 1.33 * 0.012 (thick Plaster)

= 0.01596 Cu.m

Herer calculation mortar ratio 1:8

The required amount of Cement quantity at mortar = 0.01596 Cu.m. * (1/(1+8))

= 0.01596 * 0.1111

= 0.001772 cu.m. cement requirement

Cement in k.g. = volume * density cement

Cement in k.g. = 0.001772  cu.m. * 1440 (1440 kg/m Density of cement for 50 k.g)

= 0.001772 * 1440 = 2.552 kg of cement of bag requied ment of cement in k.g.

= 2.552 / 50 (one cemnent bag weight 50 k.g. only) = 0.051033 bag

So, 100 sq.m. mortar requirement of cement = 0.051033 bag x 100 sq.m. = 5.10 bag

Sand calculation

Required amount of Sand = 0.01596 Cu.m. * (8/(1+8))

= 0.0142 Cu.m. requierd of sand for 1 Cu.m.

So,

So, 100 sq.m. mortar requirement of sand = 0.0142 Cu.m. * 100 sq.m. = 1.42 cu.m.

Also, read: Mortar Vs Grout | What Is Motor and Grout | Type of Motor and Grout | Difference Between Mortar and Grout

Labour for Rate Analysis of Plaster

As per calculation of rate analysis in labor consumption per Cu.m. requirement as per our experience or CPWD book, this book public by Central Public Works Department, Government of India for easy calculation of the rate analysis, etc.

As CPWD Mate per cu.m. 0.81 of day bhisti, per cu.m.0.27-day coolie, per cu.m. 0.81-day belder, per cu.m. 0.81-day mason, per cu.m. 0.81-day helper, per cu.m. 0.81-day mate  for water curing

Extra Work Calculation in Rate Analysis of plaster

Extra Changes in rate analysis as per below

Scaffolding 1% Extra

Transportation Cost 1%

Other Charges 2 % Extra (Electrical, and site extra expense)

Add for Water Charge @ 1% on Items Marked

Add for Contractor’s Profit @15% on Items Marked

Video tutorial for better understanding:

Like this post? Share it with your friends!

Suggested Read –

  • Brick Work Rate Analysis Calculator
  • Concrete Material Calculator | How to Work a Concrete Material Calculator
  • Trapezoidal Footing Calculator | Trapezoidal Formula | Volume of Trapezoidal Footing
  • Plaster Calculator | How to Work Plaster Calculator | What Is Plaster Calculation | How to Plaster Calculation for Wall
  • House Construction Cost Calculator | How to Work With House Construction Cost Calculator. | What Is Construction Rate

By Krunal Rajput

About Krunal Rajput

Hey, I am Krunal Rajput. The Man Behind CivilJungle. I started this site to spread knowledge about Civil Engineering. I am a Degree Holder in Civil Engineering.

You can find him on Facebook, Twitter, Tumblr, Instagram and Google News.

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

MIND BEHIND CIVILJUNGLE

Hey, I am Krunal Rajput. The Man Behind CivilJungle. I started this site to spread knowledge about Civil/Mechanical/Electrical Engineering. I am a Degree Holder in Civil Engineering.

You can find him on Facebook, Twitter, Tumblr, Instagram and Google News.

ADVERTISE

At CivilJungle, we clarify civil engineering and publish all the happenings & news of civil engineering.

Get Traffic & Exposure. We help brands optimize their online presence & performance.

MORE DETAIL

CONNECT WITH US


Privacy Policy | Contact Us | Cookie Policy | Sitemap | Sitemap for Hindi

............................... .............................. .............................

© Copyright 2019-2022 CivilJungle.com | The Content May Not Be Reproduced On Other Websites | Website Maintained By CivilJungle